Construction is progressing as they are nearing the 2nd floor pour.
Building 1 Construction
Construction is progressing and this Building will consist of only 21 units as it is only 4 stories in height.
Building 2 Completion
This building is scheduled for completion in March 2021
Construction of a covered Pavilion
Construction of a covered Pavilion along with a shuffle board and bocce ball court shall be completed by the end of January 2021 ( additional grills will be installed at the Pavilion) This will help in cleaning up and controlling the construction dust once the area is sodded.
Boat Slip Marina
The boat slip marina project shall commence around mid January 2021.